[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118580,789,1,"单选题","施工企业的施工生产计划，以（ ）为系统。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","每个建设工程项目施工",false,{"key":16,"text":17,"correct":14},"B","整个建设工程项目施工",{"key":19,"text":20,"correct":21},"C","整个施工企业",true,{"key":23,"text":24,"correct":14},"D","每个施工企业","2021\u002F2020教材P131页 施工企业的施工生产计划，属于企业计划的范畴，是以整个施工企业为系统，根据施工任务量、企业经营的需求和资源利用的可能性等，合理安排计划周期内的施工生产活动，如年度生产计划、季度生产计划、月度生产计划和旬生产计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]