[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118579,789,1,"单选题","关于施工进度计划，下列说法不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方编制的与施工进度有关的计划包括施工企业的施工生产计划和建设工程项目施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工企业的施工生产计划，以整个施工企业为系统",{"key":19,"text":20,"correct":14},"C","建设工程项目施工进度计划，以每个建设工程项目的施工为系统",{"key":22,"text":23,"correct":24},"D","建设工程项目施工进度计划，属于企业计划的范畴",true,"2021\u002F2020教材P131页 施工进度计划的类型 建设工程项目施工进度计划，属于工程项目管理的范畴。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]