[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118577,789,1,"单选题","下列选项中，一般而言属于工程项目控制性施工进度计划的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工企业年度生产计划",{"key":19,"text":20,"correct":21},"C","工程项目施工总进度计划",true,{"key":23,"text":24,"correct":14},"D","工程项目月度施工计划","2021\u002F2020教材P132页 一般而言，一个工程项目的施工总进度规划或施工总进度计划是工程 项目的控制性施工进度计划。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]