[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118574,789,1,"单选题","工程项目实施性施工进度计划的编制以()为依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工总进度规划的进度目标",false,{"key":16,"text":17,"correct":14},"B","施工总进度计划的进度目标",{"key":19,"text":20,"correct":21},"C","控制性施工进度计划确定的里程碑事件的进度目标",true,{"key":23,"text":24,"correct":14},"D","单位工程施工进度计划的进度目标","2021\u002F2020教材P133页 控制性施工进度计划的主要作用如下：（3）是编制实施性进度计划的依据",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]