[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118573,789,1,"单选题","下列进度计划中，可直接用于组织施工作业的计划是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工企业的旬生产计划",false,{"key":16,"text":17,"correct":18},"B","建设工程项目月度施工计划",true,{"key":20,"text":21,"correct":14},"C","施工企业的月度生产计划",{"key":23,"text":24,"correct":14},"D","建设工程项目施工总进度计划","2021\u002F2020教材P133页 月度施工计划和旬施工作业计划是用于直接组织施工作业的计划，它是实施性施工进度计划。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]