[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118568":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118568,789,1,"单选题","关于控制性施工进度计划的主要作用，下列表述错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","是编制与该项目相关的其他各种进度计划的依据或参考依据",false,{"key":16,"text":17,"correct":14},"B","是编制实施性进度计划的依据",{"key":19,"text":20,"correct":14},"C","论证施工总进度目标",{"key":22,"text":23,"correct":24},"D","施工各层目标的确定，明确里程碑事件的进度目标",true,"2021\u002F2020教材P133页 控制性施工进度计划的主要作用如下： （1）论证施工总进度目标；（2）施工总进度目标的分解，确定里程碑事件的进度目标；（3）是编制实施性进度计划的依据；（4）是编制与该项目相关的其他各种进度计划的依据或参考依据；（5）是施工进度动态控制的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]