[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118567,789,1,"单选题","整个项目施工进度控制的纲领性文件是()，并且也是组织和指挥施工的依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","战略性施工进度计划",false,{"key":16,"text":17,"correct":14},"B","实施性施工进度计划",{"key":19,"text":20,"correct":14},"C","竞争性施工进度计划",{"key":22,"text":23,"correct":24},"D","控制性施工进度计划",true,"2021\u002F2020教材P133页 考点是施工进度控制中的第二节施工方进度计划的类型及其作用。 控制性施工计划是整个项目施工进度控制的纲领性文件，是组织和指挥施工的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]