[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118566,789,1,"单选题","下列文件中，()是协调设计进度、物资采购计划和制定资金使用计划等的重要参考文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目年度施工进度计划",false,{"key":16,"text":17,"correct":18},"B","控制性施工进度计划",true,{"key":20,"text":21,"correct":14},"C","施工承包合同",{"key":23,"text":24,"correct":14},"D","实施性施工进度计划","2021\u002F2020教材P133页 该控制性施工进度计划是整个项目施工进度控制的纲领性文件，是组织和指挥施工的依据。当时在编制控制性施工进度计划时，初步设计还刚开始。因此它不仅是控制施工进度的依据，也是协调设计进度、物资采购计划和制定资金使用计划等的重要参考文件。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]