[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118565,789,1,"单选题","实施性施工进度计划的编制应结合工程施工的具体条件，并以（）所确定的里程碑事件的进度目标为依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目年度施工进度计划",false,{"key":16,"text":17,"correct":14},"B","项目施工总进度规划",{"key":19,"text":20,"correct":14},"C","项目施工总进度方案",{"key":22,"text":23,"correct":24},"D","项目控制性施工进度计划",true,"2021\u002F2020教材P133页 控制性施工进度计划编制的主要目的是通过计划的编制，确定施工的总体部署，确定为实现进度目标的里程碑事件的进度目标，因此实施性施工进度计划的编制应结合工程施工的具体条件，并以控制性施工进度计划所确定的里程碑事件的进度目标为依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]