[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118563,789,1,"单选题","在实施性施工进度计划中，()反映各施工作业相应的日历天的安排，以及各施工作业的施工顺序。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","年施工作业计划",false,{"key":16,"text":17,"correct":14},"B","月施工作业计划",{"key":19,"text":20,"correct":14},"C","季度施工作业计划",{"key":22,"text":23,"correct":24},"D","旬施工作业计划",true,"2021\u002F2020教材P133页 针对一个项目的旬施工作业计划应反映在这旬中，每一个施工作业（或称其为施工工 序）的名称、实物工程量、工种、每天的出勤人数、工作班次、工效、工作持续时间、所 需的施工机械名称、施工机械的数量、机械的台班产量等。旬施工作业计划还反映各施工 作业相应的日历天的安排，以及各施工作业的施工顺序。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]