[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118562,789,1,"单选题","下列施工进度计划可以用于直接组织施工作业的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","月度施工计划",true,{"key":16,"text":17,"correct":18},"B","年度施工计划",false,{"key":20,"text":21,"correct":18},"C","季度施工计划",{"key":23,"text":24,"correct":18},"D","施工总进度计划","2021\u002F2020教材P133页 月度施工计划和旬施工作业计划是用于直接组织施工作业的计划，它是实施性施工进度计划。旬施工作业计划是月度施工计划在一个旬中的具体安排。实施性施工进度计划的 编制应结合工程施工的具体条件，并以控制性施工进度计划所确定的里程碑事件的进度目 标为依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]