[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118559,789,1,"单选题","施工方应视（）的需要，编制不同深度、不同计划周期的施工计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主方",false,{"key":16,"text":17,"correct":14},"B","项目内容和项目特点",{"key":19,"text":20,"correct":21},"C","项目特点和施工进度控制",true,{"key":23,"text":24,"correct":14},"D","施工质量控制和项目特点","2021\u002F2020教材P131页 在进度计划编制方面，施工方应视项目的特点和施工进度控制的需要，编制深度不同的控制性和直接指导项目施工的进度计划，以及按不同计划编制的计划，如年度、季度、月度和旬计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]