[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118554,789,1,"单选题","施工方进度控制的任务是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","根据施工任务委托合同对施工进度的要求控制施工进度",true,{"key":16,"text":17,"correct":18},"B","控制整个项目实施阶段的进度",false,{"key":20,"text":21,"correct":18},"C","依据施工组织设计对施工进度的要求控制施工进度",{"key":23,"text":24,"correct":18},"D","依据建设单位对项目动用要求控制施工进度","2021\u002F2020教材P131页 施工方进度是依据施工任务委托合同对施工进度的要求控制施工工作进度，这是施工方履行合同的义务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]