[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118553,789,1,"单选题","在进度计划编制方面，施工方应视()的需要，编制深度不同的控制性和直接指导项目施工的进度计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工的特点和施工进度控制",false,{"key":16,"text":17,"correct":14},"B","项目的特点和施工成本控制",{"key":19,"text":20,"correct":21},"C","项目的特点和施工进度控制",true,{"key":23,"text":24,"correct":14},"D","施工的特点和施工成本控制","2021\u002F2020教材P131页 施工方进度控制的任务是依据施工任务委托合同对施工进度的要求控制施工工作进度，这是施工方履行合同的义务。在进度计划编制方面，施工方应视项目的特点和施工进度控制的需要，编制深度不同的控制性和血接指导项目施工的进度计划，以及按不同计划周期编制的计划，如年度、季度、月度和旬计划等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]