[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118552,789,1,"单选题","施工单位进度控制的任务是依据()控制施工工作进度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主方对施工进度的要求",false,{"key":16,"text":17,"correct":18},"B","施工任务承包合同对施工进度的要求",true,{"key":20,"text":21,"correct":14},"C","建筑施工工期定额",{"key":23,"text":24,"correct":14},"D","业主方对施工进度的要求和工期定额等","2021\u002F2020教材P131页 施工方进度控制的任务是依据施工任务委托合同对施工进度的要求控制施工工作进度，这是施工方履行合同的义务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]