[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118549,789,1,"单选题","建设项目设计方进度控制的任务是依据()对设计工作进度的要求，控制设计工作进度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计大纲",false,{"key":16,"text":17,"correct":18},"B","设计任务委托合同",true,{"key":20,"text":21,"correct":14},"C","设计总进度纲要",{"key":23,"text":24,"correct":14},"D","可行性研究报告","2021\u002F2020教材P131页 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。另外，设计方应尽可能使设计工作的进度与招标、施工和物资采购等工作进度相协调。在国际上，设计进度计划主要是确定各设计阶段的设计图纸（包括有关的说明）的出图计划，在出图计划中标明每张图纸的出图日期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]