[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118548,789,1,"单选题","下列建设工程项目进度控制工作中，属于设计方进度控制任务的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","部署项目动用准备工作进度",false,{"key":16,"text":17,"correct":18},"B","协调设计、招标的工作进度",true,{"key":20,"text":21,"correct":14},"C","编制项目施工的工作进度",{"key":23,"text":24,"correct":14},"D","编制供货进度计划","2021\u002F2020教材P131页 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。另外，设计方应尽可能使设计工作的进度与招标、施工和物资采购等工作进度相协调。在国际上，设计进度计划主要是确定各设计阶段的设计 图纸（包括有关的说明）的出图计划，在出图计划中标明每张图纸的出图日期。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]