[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118547,789,1,"单选题","关于设计方进度控制的说法，不正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计方进度控制的任务是依据设计任务委托合同来对设计工作进度进行控制",false,{"key":16,"text":17,"correct":14},"B","设计方的进度控制是履行其设计任务委托合同的义务",{"key":19,"text":20,"correct":21},"C","设计进度计划主要是概念设计和初步设计阶段的设计图纸的出图计划",true,{"key":23,"text":24,"correct":14},"D","设计方应尽可能使设计进度与招标、施工和物资采购等进度相协调","2021\u002F2020教材P131页 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。另外，设计方应尽可能使设计工作的进度与招标、施工和物资采购等丁作进度相协调。在国际上，设计进度计划主要是确定各设计阶段的设计图纸（包括有关的说明）的出图计划，在出图计划中标明每张图纸的出图日期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]