[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118546,789,1,"单选题","只重视进度计划的编制，不重视进度计划必要的调整，则（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度无法完成",false,{"key":16,"text":17,"correct":14},"B","进度需要调整",{"key":19,"text":20,"correct":14},"C","进度同样可以得到控制",{"key":22,"text":23,"correct":24},"D","进度无法得到控制",true,"2021\u002F2020教材P131页 如只重视进度计划的编制，而不重视进度计划必要的调整，则进度无法得到控制。进度控制的过程是在确保进度目标的前提下，在项目进展的过程中不断调整进度计划的过程。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]