[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118545":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118545,789,1,"单选题","建设工程项目进度控制工作包括:①编制进度计划;②调整进度计划;③进度目标的分析和论证;④跟踪检査计划的执行情况。其正确的工作程序是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①一②一③一④",false,{"key":16,"text":17,"correct":14},"B","③一①一②一④",{"key":19,"text":20,"correct":21},"C","③一①一④一②",true,{"key":23,"text":24,"correct":14},"D","④一②一③一①","2021\u002F2020教材P131页 建设项目是在动态条件下实施的,进度控制也就必须是一个动态的管理过程,它由下列环节组成:(1)进度目标的分析和论证;(2)在收集资料和调查研究的基础上编制进度计划;(3)定期跟踪检査所编制的进度计划执行情况,若其执行有偏差,则采取纠偏措施,并视必要调整进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]