[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118544,789,1,"单选题","建设工程项目进度控制的工作环节包括进度目标的分析论证，进度计划的编制、执行以及对执行情况的检查和( )等。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","纠偏",true,{"key":16,"text":17,"correct":18},"B","分析",false,{"key":20,"text":21,"correct":18},"C","总结",{"key":23,"text":24,"correct":18},"D","报告","2021\u002F2020教材P131页 建设工程项目进度控制的工作环节包括进度目标的分析论证，进度计划的编制，执行及对执行情况的检查和纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]