[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118543,789,1,"单选题","供货方进度控制的任务是依据()对供货的要求控制供货工作进度，这是供贷方履行合同的义务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","供货合同",true,{"key":16,"text":17,"correct":18},"B","施工工序",false,{"key":20,"text":21,"correct":18},"C","业主",{"key":23,"text":24,"correct":18},"D","施工总进度计划","2021\u002F2020教材P131页 供货方进度控制的任务是依据供货合同对供货的要求控制供货工作进度，这是供货 方履行合同的义务。供货进度计划应包括供货的所有环节， 如采购、加工制造、运 输等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]