[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118541,789,1,"单选题","建设工程项目按不同功能编制的进度计划系统包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总进度规划、子系统进度规划、子系统中的单项工程进度计划",false,{"key":16,"text":17,"correct":18},"B","控制性、指导性和实施性进度计划",true,{"key":20,"text":21,"correct":14},"C","业主方计划、施工方计划和货方计划",{"key":23,"text":24,"correct":14},"D","年度计划、季度计划、月度计划","2021\u002F2020教材P130页 由不同功能的计划构成的进度计划系统包括：(1) 控制性进度规划（计划）；(2) 指导性进度规划（计划）；(3) 实施性(操作性）进度计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]