[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118540,789,1,"单选题","建设工程项目的业主和参与方都有进度控制的任务，各方()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制的目标和时间范畴各不相同",true,{"key":16,"text":17,"correct":18},"B","控制的目标和时间范畴均相同",false,{"key":20,"text":21,"correct":18},"C","控制的目标不同、但控制的时间范畴相同",{"key":23,"text":24,"correct":18},"D","控制的目标相同、但控制的时间范畴不同","2021\u002F2020教材P130页 建设工程项目管理有多种类型，代表不同方利益的项目管理（业主方和项目参与各方）都有进度控制的任务。但是，其控制的目标和时间范畴是不相同的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]