[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118539,789,1,"单选题","在建设工程项目进度计划系统中各进度计划或各子系统进度计划编制和调整时必须注意（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","各进度计划的相对独立",false,{"key":16,"text":17,"correct":18},"B","其相互间的联系和协调",true,{"key":20,"text":21,"correct":14},"C","各进度计划的结构分析",{"key":23,"text":24,"correct":14},"D","项目结构分析","2021\u002F2020教材P130页 在建设工程项目进度计划系统中各进度计划或各子系统进度计划编制和调整时必须注意 其相互间的联系和协调。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]