[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118537,789,1,"单选题","建设工程项目进度计划系统中，年度、季度、月度和旬计划属于()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由不同深度的计划构成的进度计划系统",false,{"key":16,"text":17,"correct":14},"B","由不同功能的计划构成的进度计划系统",{"key":19,"text":20,"correct":14},"C","由不同项目参与方的计划构成的进度计划系统",{"key":22,"text":23,"correct":24},"D","由不同周期的计划构成的进度计划系统",true,"2021\u002F2020教材P130页 由不同周期的计划构成的进度计划系统包括： (1) 5年（或多年）建设进度计划；(2)年度、季度、月度和旬计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]