[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118536,789,1,"单选题","大型建设工程项目总进度目标论证的核心工作是通过( )论证总进度目标实现的可能性。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程实施条件分析",false,{"key":16,"text":17,"correct":18},"B","编制总进度纲要",true,{"key":20,"text":21,"correct":14},"C","编制施工进度计划及相关的资源需求计划",{"key":23,"text":24,"correct":14},"D","编制多个不同的建设工程项目进度计划系统","2021\u002F2020教材P129页 总进度目标论证并不是单纯的总进度规划的编制工作，它涉及许多工程实施的条件分析和工程实施策划方面的问题。大型建设工程项目总进度目标论证的核心工作是通过编制总进度纲要论证总进度目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]