[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118534,789,1,"单选题","建设工程项目总进度目标论证的工作包括：①确定项目的工作编码；②调查研究和收集资料；③进行项目结构分析；④进行进度计划系统的结构分析；⑤编制各层（各级）进度计划等。其正确的工作步骤为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①—⑤—②—③—④",false,{"key":16,"text":17,"correct":14},"B","②—⑤—①—④—③",{"key":19,"text":20,"correct":14},"C","①—④—②—⑤—①",{"key":22,"text":23,"correct":24},"D","②—③—④—①—⑤",true,"2021\u002F2020教材P129页 本题考查的是总进度目标。建设工程项目总进度目标论证的工作步骤如下：调查研究和收集资料→进行项目结构分析→进行进度计划系统的结构分析→确定项目的工作编码→编制各层（级）进度计划→协调各层进度计划的关系和编制总进度计划→若所编制的总进度计划不符合项目的进度目标，则设法调整→若经过多次调整，进度目标无法实现，则报告项目决策者。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]