[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118533,789,1,"单选题","建设工程项目总进度纲要的主要内容包括：①项目实施的总体部署；②总进度规划；③各子系统进度规划；④确定里程碑事件的计划进度目标。下列顺序正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④",true,{"key":16,"text":17,"correct":18},"B","②→①→③→④",false,{"key":20,"text":21,"correct":18},"C","③→①→②→④",{"key":23,"text":24,"correct":18},"D","④→①→②→③","2021\u002F2020教材P129页 总进度纲要的主要内容包括：(1)项目实施的总体部署；(2)总进度规划；(3)各子系统进度规划；(4)确定里程碑事件的计划进度目标；(5)总进度目标实现的条件和应采取的措施等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]