[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118531,789,1,"单选题","下列选项中，不属于总进度纲要主要内容的有()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目实施的总体部署",false,{"key":16,"text":17,"correct":14},"B","总进度规划",{"key":19,"text":20,"correct":14},"C","确定里程碑事件的计划进度目标",{"key":22,"text":23,"correct":24},"D","施工进度计划及相关的资源需求计划",true,"2021\u002F2020教材P129页 总进度纲要的主要内容包括： （1）项目实施的总体部署；（2）总进度规划；（3）各子系统进度规划；（4）确定里程碑事件的计划进度目标；（5）总进度目标实现的条件和应采取的措施等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]