[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118530":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118530,789,1,"单选题","大型建设工程项目总进度目标论证的核心工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目结构分析",false,{"key":16,"text":17,"correct":14},"B","编制各层进度计划",{"key":19,"text":20,"correct":21},"C","通过编制总进度纲要论证总进度目标实现的可能性",true,{"key":23,"text":24,"correct":14},"D","协调各层进度计划的关系，编制总进度计划","2021\u002F2020教材P129页 有原文大型建设工程项目总进度目标论证的核心工作通过编制总进度纲要论证总进度目标实现的可能性",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]