[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118529,789,1,"单选题","某市拟新建一办公大楼，项目建设单位组织有关专家对该项目的总进度目标进行论证，在调查研究和收集整理后，紧接着应进行的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行进度计划系统结构分析",false,{"key":16,"text":17,"correct":18},"B","进行项目结构分析",true,{"key":20,"text":21,"correct":14},"C","编制各级进度计划",{"key":23,"text":24,"correct":14},"D","确定工作编码","2021\u002F2020教材P129页 建设工程项目总进度目标论证的工作步骤如下：（1）调查研究和收集资料；（2）进行项目结构分析；（3）进行进度计划系统的结构分析；（4）确定项目的工作编码；（5）编制各层（各级）进度计划；（6）协调各层进度计划的关系和编制总进度计划；（7）若所编制的总进度计划不符合项目的进度目标，则设法调整；（8）若经过多次调整，进度目标无法实现，则报告项目决策者。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]