[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118528,789,1,"单选题","进行建设工程项目总进度目标控制前，首先应分析和论证目标实现的可能性。在调查研究和收集整理后，紧接着应进行的工作是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行进度计划系统结构分析",false,{"key":16,"text":17,"correct":18},"B","进行项目结构分析",true,{"key":20,"text":21,"correct":14},"C","编制各级进度计划",{"key":23,"text":24,"correct":14},"D","确定工作编码","2021\u002F2020教材P129页 建设工程项目总进度目标论证的工作步骤如下：(1)调查研究和收集资料；(2)进行项目结构分析；(3)进行进度计划系统的结构分析",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]