[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118527":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118527,789,1,"单选题","某大型建设工程项目总进度目标论证的部分工作包括：①进行进度计划系统的结构分析；②确定项目的丁作编码；③协调各层进度计划的关系和编制总进度计划；④编制各层（各级）进度计划；⑤进行项目结构分析；⑥调查研究和收集资料。其正确的步骤是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑥②⑤③①④",false,{"key":16,"text":17,"correct":18},"B","⑥⑤①②④③",true,{"key":20,"text":21,"correct":14},"C","⑥③①②⑤④",{"key":23,"text":24,"correct":14},"D","⑥①⑤③②④","2021\u002F2020教材P129页 建设工程项目总进度目标论证的工作步骤如下：(1)调查研究和收集资料；(2)进行项口结构分析；(3)进行进度计划系统的结构分析；(4)确定项目的工作编码；(5)编制各层（各级）进度计划；(6)协调各层进度计划的关系和编制总进度计划；(7)若所编制的总进度计划不符合项目的进度目标，则设法调整；(8)若经过多次调整，进度目标无法实现，则报告项目决策者。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]