[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118524":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118524,789,1,"单选题","根据建设工程项目总进度目标论证的工作步骤，在完成“项目结构分析”工作之后立即进行的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查研究和搜集资料",false,{"key":16,"text":17,"correct":18},"B","进度计划系统的结构分析",true,{"key":20,"text":21,"correct":14},"C","项目的工作编码",{"key":23,"text":24,"correct":14},"D","编制各层进度计划","2021\u002F2020教材P129页 建设工程项目总进度目标论证的工作步骤如下： (1)调查研究和收集资料； (2)进行项目结构分析； (3)进行进度计划系统的结构分析： (4)确定项目的工作编码； (5)编制各层（各级）进度计划； (6)协调各层进度计划的关系和编制总进度计划； (7)若所编制的总进度计划不符合项目的进度目标，则设法调整； (8)若经过多次调整，进度目标无法实现，则报告项目决策者。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]