[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118521,789,1,"单选题","建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，这是（ ）的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目实施",false,{"key":16,"text":17,"correct":18},"B","项目进度控制",true,{"key":20,"text":21,"correct":14},"C","编制总进度纲要",{"key":23,"text":24,"correct":14},"D","进行项目结构分析","2021\u002F2020教材P129页 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]