[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118520,789,1,"单选题","大型建设工程项目总进度目标论证的核心工作是通过（ ）论证进度目标实现的可能性。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","指导进度规划",false,{"key":16,"text":17,"correct":14},"B","拟订工程项目总进度计划",{"key":19,"text":20,"correct":21},"C","编制总进度纲要",true,{"key":23,"text":24,"correct":14},"D","绘制工程项目进度平衡表","2021\u002F2020教材P129页 大型建设项目总进度目标论证的核心工作是通过编制总进度纲要论证总进度目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]