[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118518,789,1,"单选题","大型建设工程项目总进度论证的核心工作是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确进度控制的措施",false,{"key":16,"text":17,"correct":14},"B","分析影响施工进度且目标实现的主要因素",{"key":19,"text":20,"correct":21},"C","通过编制总进度纲要论证总进度目标实现的可能性",true,{"key":23,"text":24,"correct":14},"D","编制各层（各级）进度计划","2021\u002F2020教材P129页 大型建设工程项目总进度目标论证的核心工作是通过编制总进度纲要论证总进度目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]