[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118513,789,1,"单选题","项目进度控制的主要工作环节中，首先应进行的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制进度计划",false,{"key":16,"text":17,"correct":18},"B","分析和论证进度目标",true,{"key":20,"text":21,"correct":14},"C","定期跟踪进度计划的执行情况",{"key":23,"text":24,"correct":14},"D","采取纠偏措施","2021\u002F2020教材P128页 本题考查的是项目进度控制的目的。进度控制是一个动态的管理过程，包括：(1)进度目标的分析和论证，其目的是论证进度目标是否合理，进度目标有否可能实现。如果经过科学的论证，目标不可能实现，则必须调整目标;(2)在收集资料和调查研究的基础上编制进度计划;(3)进度计划的跟踪检查与调整：包括定期跟踪检查所编制进度计划的执行情况，若其执行有偏差，则采取纠偏措施，并视必要调整进度计划。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]