[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118512,789,1,"单选题","在进行建设工程项目总进度目标控制前，首先应分析和论证( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标实现的可能性",true,{"key":16,"text":17,"correct":18},"B","目标计划的可行性",false,{"key":20,"text":21,"correct":18},"C","目标完成的收益情况",{"key":23,"text":24,"correct":18},"D","目标实施的步骤","2021\u002F2020教材P128页 建设工程项目总进度目标的内涵 在进行建设工程总进度目标控制前，首先应分析和论证目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]