[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118511":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118511,789,1,"单选题","在项目的实施阶段，关于项目总进度和施工进度的说法正确的是( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目总进度主要是施工进度",false,{"key":16,"text":17,"correct":14},"B","项目总进度主要包括设计、施工进度",{"key":19,"text":20,"correct":14},"C","项目总进度包括设计、施工前准备、工程施工和设备安装、工程物资采购等工作进度",{"key":22,"text":23,"correct":24},"D","项目总进度包括设计前准备阶段、设计、招标、施工前准备，工程施工和设备安装、工程物资采购，项目动用前准备等工作进度",true,"2021\u002F2020教材P128页 在项目的实施阶段，项目总进度不仅只是施工进度，它包括：（1）设计前准备阶段的工作进度，（2）设计工作进度，（3）招标工作进度，（4）施工前准备工作进度，（5）工程施工和设备安装工作进度，（6）工程物资采购工作进度，（7）项目动前准备工作进度等",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]