[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118510,789,1,"单选题","建设工程项目的总进度目标指的是整个项目的进度目标，在进行建设工程项目总进度目标控制前，首先应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","制定总进度目标",false,{"key":16,"text":17,"correct":18},"B","分析和论证目标实现的可能性",true,{"key":20,"text":21,"correct":14},"C","论证总进度纲要",{"key":23,"text":24,"correct":14},"D","确定里程碑事件及进度计划与目标","2021\u002F2020教材P128页 在进行建设工程项目总进度目标控制前，首先应分析和论证目标实现的可能性。若项目总进度 目标不可能实现，则项目管理者应提出调整项目总进度目标的建议，提请项目决策者审议。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]