[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118509,789,1,"单选题","在进行建设工程项目总进度目标控制前，首先应该()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分析项目的合同结构",false,{"key":16,"text":17,"correct":14},"B","编制详细的网络计划",{"key":19,"text":20,"correct":14},"C","分析项目资金流量",{"key":22,"text":23,"correct":24},"D","分析进度目标实现的可能性",true,"2021\u002F2020教材P128页 在进行 建设工程项目总进度目标控制前，首先应分析和论证目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]