[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118504,789,1,"单选题","建设工程项目的总进度目标指的是整个项目的进度目标，它是在()阶段项目定义时确定的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目审批",false,{"key":16,"text":17,"correct":14},"B","项目实施",{"key":19,"text":20,"correct":14},"C","项目定义",{"key":22,"text":23,"correct":24},"D","项目决策",true,"2021\u002F2020教材P128页 建设工程项目的总进度目标指的是整个项目的进度目标，它是在项目决策阶段项目定义时确定的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]