[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118502,789,1,"单选题","育才中学的教学楼工程由甲设计院设计，由乙建筑公司进行施工总承包，则教学楼建设工程项目实施阶段的总进度目标控制应当由( )来进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","甲设计院",false,{"key":16,"text":17,"correct":14},"B","乙建筑公司",{"key":19,"text":20,"correct":21},"C","育才中学",true,{"key":23,"text":24,"correct":14},"D","项目经理","2021\u002F2020教材P128页 建设项目总进度目标的控制是业主方的项目管理的任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]