[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118501,789,1,"单选题","建设工程项目总进度目标的控制是（ ）项目管理的任务之一。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工总承包方",false,{"key":16,"text":17,"correct":14},"B","设计方",{"key":19,"text":20,"correct":14},"C","施工方和设计方",{"key":22,"text":23,"correct":24},"D","业主方",true,"2021\u002F2020教材P128页 建设工程项目总进度目标的控制是业主方项目管理的任务（若采用建设项目总承包的模式，协助业主进行项目总进度目标的控制也是建设项目总承包方项目管理的任务）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]