[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118500,789,1,"单选题","下列关于费用（进度）偏差和费用（进度）绩效指数的说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用（进度）偏差反映的是相对偏差",false,{"key":16,"text":17,"correct":14},"B","费用（进度）绩效指数反映的是绝对偏差",{"key":19,"text":20,"correct":21},"C","费用（进度）偏差仅适合于对同一项目作偏差分析",true,{"key":23,"text":24,"correct":14},"D","费用（进度）绩效指数受项目层次和项目实施时间的限制","2021\u002F2020教材P113页 费用（进度）偏差反映的是绝对偏差，费用（进度）偏差仅适合于对同一项目作偏差分析。费用（进度）绩效指数反映的是相对偏差，它不受项目层次的限制，也不受项目实施时间的限制，因而在同一项目和不同项目比较中均可采用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]