[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118491":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118491,789,1,"单选题","编制竞争性成本计划的依据，不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标文件中的合同条件",false,{"key":16,"text":17,"correct":14},"B","投标者须知",{"key":19,"text":20,"correct":14},"C","工程量清单",{"key":22,"text":23,"correct":24},"D","项目实施方案",true,"2021\u002F2020教材P101页 竞争性成本计划即工程项目投标及签订合同阶段的估算成本计划。这类成本计划是以招标文件中的合同条件、投标者须知、技术规程、设计图纸或工程量清单等为依据，以有关价格条件说明为基础，结合调研和现场考察获得的情况，根据本企业的工料消耗标准、水平、价格资料和费用指标，对本企业完成招标工程所需要支出的全部费用的估算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]