[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118490,789,1,"单选题","某工程项目有4800m3的土方开挖任务，交由某分包商承担，计划在6个月完成，预算单价为580元\u002Fm3。开工后发现实际单价为600元\u002Fm3。工程进行了3个月，累计完成工程量3000m3.运用赢得值法分析，至第3个月底的进度偏差为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-34.8",false,{"key":16,"text":17,"correct":14},"B","-6",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","34.8",true,"2021\u002F2020教材P112页 进度偏差(SV)=已完工作预算费用(BCWP)计划工作预算费用(BCWS)进度偏差=3000×580-（4800\u002F6×3）×580=34.8",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]