[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118488,789,1,"单选题","建设工程项目施工成本控制应贯穿于项目从()开始直到()的全过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标阶段，竣工验收",false,{"key":16,"text":17,"correct":18},"B","投标阶段，保证金返还",true,{"key":20,"text":21,"correct":14},"C","招标阶段，保修期结束",{"key":23,"text":24,"correct":14},"D","投标阶段，保修期结束","2021\u002F2020教材P99页 建设工程项目施工成本控制应贯穿于项目从投标阶段开始直至保证金返还的全过程，它是企业全面成本管理的重要环节。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]